TuLlave: Bogotá's concession-run fare card & preloaded free trips
This overview was generated with AI from the public sources listed below and checked against them before publication. It has not had a complete human fact-check — treat it as a starting point and follow the sources.
18 sourced claims on this page, none individually verified yet — turn on “Sources in the text” to see each one.
How this atlas is made · What “last verified” means · What “source-checked” means · The full record behind this page
Collection is outsourced, the risk is not. Three tribunals ruled for the private concessionaire, leaving fare evasion, about 295 billion pesos of it in 2025, with the public agency.
what does this mean?
The strongest source is the operator's or the city's own reporting — an official report, dataset or press release. It grades who did the looking — not how well the project went. All four grades →Part of 1001 Smart Cities — 1,247 documented projects · 🏙️ 12 more in Bogotá · 🎫 Smart ticketing guide · 🚲 Mobility projects
TuLlave, issued by the private concessionaire Recaudo Bogotá under a contract signed in 2011 and running to 2028, is the single card for TransMilenio's trunk buses, the zonal SITP fleet and the TransMiCable gondolas, with free transfers inside a 125-minute window — on personalised cards only. On 1 February 2025 the city abolished the discounted fare for poor, elderly and disabled riders and instead began preloading their cards with free trips, 1 to 12 a month depending on Sisbén band. In January 2026 bank cards were read at just two stations, at the full COP 3,550 fare and with no transfer, so the open loop costs more than the card. Three arbitration tribunals have ruled for the concessionaire, one of them placing responsibility for fare-evasion control on TransMilenio S.A. rather than on the collector; evasion cost the system about 295 billion pesos in 2025. In 2026 the city tendered a five-year concession for an interoperable collection system meant to take bank cards, QR codes and phones across TransMilenio, the metro and Regiotram; TuLlave is to keep running during the transition.
📊 Impact
More than 636,000 people received preloaded free trips in 2025, against the city's launch projection of about 820,000 — 294,000 aged over 62, 106,000 with disabilities and 236,000 living in poverty (city figures).
🎓 Lesson
Outsourcing collection is not the same as outsourcing the risk: three tribunals kept the concessionaire's revenue whole while leaving the fare-evasion loss with the public agency.
Sources
Show 8 more sourcesShow fewer
📅 How old is the evidence?
Two clocks, kept apart: when this entry’s sources were published, and what has happened to its record in the atlas. Documented span: since 2012. 10 of 13 sources carry a publication date, from 5 July 2016 to 16 August 2026.
When the sources were published
- El Tiempo · pressEl Tiempo — how TransMilenio cards were cloned (5 Jul 2016)
- El Tiempo · pressEl Tiempo — why TransMilenio has lost three tribunal rulings to Recaudo Bogotá (June 2023)
- Alcaldía Mayor de Bogotá · city governmentAlcaldía de Bogotá — new transport subsidy scheme, 2025
- TuLlave (TransMilenio S.A. fare system) · operatorTuLlave — Mastercard and Visa digital payments in the system
- Alcaldía Mayor de Bogotá · city governmentAlcaldía de Bogotá — 2026 fare adjustment (Abecé)
- El Tiempo · pressEl Tiempo — bank cards and phones enabled at TransMilenio stations (19 Jan 2026)
- Concejo de Bogotá · city councilConcejo de Bogotá — evasion cost the city more than COP 265bn in 2025
- Semana · pressSemana — the plan to integrate metro and TransMilenio payment (4 Mar 2026)
Show 2 more dated sourcesShow fewer
- Noticias RCN · pressNoticias RCN — fare evasion losses reach COP 295bn a year (10 Jul 2026)
- Publimetro Colombia · pressPublimetro — new collection system changes concessionaire, not dependency (16 Aug 2026)
Show your work What this page rests on and what it can’t tell you · all 18 claims with their sources · the forensic record
Evidence file · public beta 18 addressable claims, 13 source dossiers, one permanent baseline. The file is unreviewed — an AI-assisted structural migration, not a human or expert endorsement. Every revision keeps a permanent copy under revision history.
Inspect the claims, one by one — verbatim text, sources and caveats for all 18
The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-23df9d97a66b351b
quantitative
issued by the private concessionaire Recaudo Bogotá under a contract signed in 2011 and running to 2028
Sources carrying this claim
clm-7ab80b683d1952a0
descriptive
is the single card for TransMilenio's trunk buses, the zonal SITP fleet and the TransMiCable gondolas
Sources carrying this claim
clm-80f3036acd5ccc4a
quantitative
with free transfers inside a 125-minute window — on personalised cards only
Sources carrying this claim
clm-2c5f630472fd5a11
quantitative
On 1 February 2025 the city abolished the discounted fare for poor, elderly and disabled riders and instead began preloading their cards with free trips
Sources carrying this claim
clm-349049367ad64356
quantitative
1 to 12 a month depending on Sisbén band
Sources carrying this claim
clm-2b0b8a89783f01d2
quantitative
In January 2026 bank cards were read at just two stations
Sources carrying this claim
clm-48a0829fa8fd8e8c
quantitative
at the full COP 3,550 fare and with no transfer
Sources carrying this claim
clm-a0e5bb6de36c3464
descriptive
so the open loop costs more than the card
Sources carrying this claim
clm-465b9d1c23203bde
descriptive
Three arbitration tribunals have ruled for the concessionaire
Sources carrying this claim
clm-1294f2f9575050c1
descriptive
one of them placing responsibility for fare-evasion control on TransMilenio S.A. rather than on the collector
Sources carrying this claim
clm-13d89d8c35624301
quantitative
evasion cost the system about 295 billion pesos in 2025
Sources carrying this claim
clm-9cfb7a7f932fbb7b
quantitative
In 2026 the city tendered a five-year concession for an interoperable collection system
Sources carrying this claim
clm-9c8690c8d397b9c2
descriptive
meant to take bank cards, QR codes and phones across TransMilenio, the metro and Regiotram
Sources carrying this claim
clm-71b12072166800e6
descriptive
TuLlave is to keep running during the transition
Sources carrying this claim
clm-b32d6353036affcf
quantitative
More than 636,000 people received preloaded free trips in 2025
Sources carrying this claim
clm-01937c2e6274435a
quantitative
against the city's launch projection of about 820,000
Sources carrying this claim
clm-5056ee841817aa5a
quantitative
294,000 aged over 62, 106,000 with disabilities and 236,000 living in poverty
Sources carrying this claim
clm-c3e245ee9a02d80f
descriptive
three tribunals kept the concessionaire's revenue whole while leaving the fare-evasion loss with the public agency
Sources carrying this claim
Forensic record — source dossiers, gaps, hashes and the exact revision this page renders
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:3953721124a3879bab6191b8f5a5537fef8ef82828230934ad4885deb309e1ca
- 18
- of 18 claims mapped
- 13
- source dossiers
- 10
- publication dates recorded
- 0
- archives linked
- 0
- exact locators
- 0
- content captures hashed
Governance facts carried by the record
- Operator
- Recaudo Bogotá S.A.S., under concession to TransMilenio S.A.
- Actor types
- private
- Funding model
- ppp
- Funding description
- Fare revenue under concession contract 001 of 2011; free trips funded from the district budget
- Cost
- Not recorded
- Ownership
- Not recorded
- Decision rights
- Not recorded
- Exit conditions
- Not recorded
13 source dossiers
TuLlave (Recaudo Bogotá / TransMilenio) — card benefits
- Stable source ID
src-5ef0a57b4406819c- Publisher
- Name not classified · tullaveplus.gov.co
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-11-03
- Dossier created
- 2026-11-04
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Operator page. Carries the 125-minute transfer window ("habilitando la ventana de tiempo de los 125 minutos"), the two-trip credit facility, balance protection after blocking, and the list of covered services: troncal, zonal (urban/complementary/special), dual and TransMiCable.
- Claims linked
Alcaldía de Bogotá — 2026 fare adjustment (Abecé)
- Stable source ID
src-124603d3c3630e91- Publisher
- Name not classified · bogota.gov.co
- Type / language
- web-page · language not classified
- Published
- 2026-01-09
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-11-03
- Dossier created
- 2026-11-04
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
City notice on the 2026 fare: a single COP 3,550 fare for TransMilenio, TransMiZonal and TransMiCable from 14 January 2026 (+10.9%), free transfers within 125 minutes on personalised cards only, and more than 636,000 people given free trips in 2025 (294,000 older people, 106,000 with disabilities, 236,000 in poverty); for 2026 it projects more than 600,000 beneficiaries and about COP 60bn.
Alcaldía de Bogotá — new transport subsidy scheme, 2025
- Stable source ID
src-7449acb34c036b8a- Publisher
- Name not classified · bogota.gov.co
- Type / language
- web-page · language not classified
- Published
- 2025-01-18
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-11-03
- Dossier created
- 2026-11-04
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Carries the start date ("a partir del 1 de febrero de 2025"), the monthly free-trip bands (1–12 for people with disabilities, 1–8 for over-62s, 5–7 for poor households, by Sisbén IV level A1–B7), the abolition of the previous discount ("Los descuentos en tarifas actuales serán reemplazados por los pasajes gratuitos") and the projection of "aproximadamente 820.000 personas" — a projection the 2026 notice does not confirm; delivery reached 636,000.
TuLlave — Mastercard and Visa digital payments in the system
- Stable source ID
src-20eed8b3f47d3dda- Publisher
- Name not classified · tullaveplus.gov.co
- Type / language
- web-page · language not classified
- Published
- 2025-01-28
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-11-03
- Dossier created
- 2026-11-04
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Operator announcement of the open-loop pilot: three readers at Portal Norte from December 2024, fare then COP 3,200, and the explicit condition "tarifa plena y no aplican transbordos" — the transfer benefit is reserved for personalised TuLlave cards.
- Claims linked
- Background source; no baseline claim points here
El Tiempo — bank cards and phones enabled at TransMilenio stations (19 Jan 2026)
- Stable source ID
src-1539dee585468791- Publisher
- Name not classified · eltiempo.com
- Type / language
- web-page · language not classified
- Published
- 2026-01-19
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-11-03
- Dossier created
- 2026-11-04
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Establishes the current footprint of the open loop: validators at Portal Norte–Unicervantes and El Tiempo–Cámara de Comercio only, charging the full COP 3,550 fare from 14 January 2026, with free transfers lost. Confirms TuLlave remains the only route to a transfer.
El Tiempo — why TransMilenio has lost three tribunal rulings to Recaudo Bogotá (June 2023)
- Stable source ID
src-9dda089b8ae173be- Publisher
- Name not classified · eltiempo.com
- Type / language
- web-page · language not classified
- Published
- 2023-06-05
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-11-03
- Dossier created
- 2026-11-04
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Load-bearing for the ownership question: concession signed August 2011 and running to 2028; December 2016 award of COP 6,511m (COP 25,092m with interest); May 2021 tribunal awarding no money but holding TransMilenio responsible for evasion control; 2023 award of COP 76,417m. El Espectador reported the same 2023 award at about COP 74bn (headline verified by search; the article itself was not fetched), so the entry states the finding, not a single exact figure.
Noticias RCN — fare evasion losses reach COP 295bn a year (10 Jul 2026)
- Stable source ID
src-b3f5137bd89d1c8a- Publisher
- Name not classified · noticiasrcn.com
- Type / language
- web-page · language not classified
- Published
- 2026-07-10
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-11-03
- Dossier created
- 2026-11-04
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Counterweight, citing Concejo de Bogotá data: 83 million fare evasions in 2025, losses close to COP 295,000 millones, about 227,000 people entering without paying each day, and full-height turnstiles installed at 21 stations.
- Claims linked
Concejo de Bogotá — evasion cost the city more than COP 265bn in 2025
- Stable source ID
src-428422cacca12e89- Publisher
- Name not classified · concejodebogota.gov.co
- Type / language
- web-page · language not classified
- Published
- 2026-02-12
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-11-03
- Dossier created
- 2026-11-04
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Council release whose headline states that evasion cost the city more than COP 265bn in 2025 — a lower figure than the COP 295bn the press attributes to council data.
- Claims linked
- Background source; no baseline claim points here
Semana — the plan to integrate metro and TransMilenio payment (4 Mar 2026)
- Stable source ID
src-f0986e110f5ea792- Publisher
- Name not classified · semana.com
- Type / language
- web-page · language not classified
- Published
- 2026-03-04
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-11-03
- Dossier created
- 2026-11-04
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Currency check: the Secretaría Distrital de Movilidad opened tender LP-10-2026 for a Sistema Interoperable de Recaudo, targeted for October 2027, to cover the metro and Regiotram de Occidente alongside the existing system. The article does not state who will own the new system or its data.
- Claims linked
El Tiempo — how TransMilenio cards were cloned (5 Jul 2016)
- Stable source ID
src-5cd5e04dd1b31511- Publisher
- Name not classified · eltiempo.com
- Type / language
- web-page · language not classified
- Published
- 2016-07-05
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-11-03
- Dossier created
- 2026-11-04
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Corrects the obvious assumption: the fraud of more than COP 27,000 millones hit the legacy red and blue Angelcom cards (Cliente Frecuente and Monedero), roughly 15 million of which were still circulating, not TuLlave; officials described the green card as using banking-grade technology. Cloned cards were finished with green stickers to pass as TuLlave.
- Claims linked
- Background source; no baseline claim points here
Datos Abiertos Bogotá — TransMilenio S.A. datasets
- Stable source ID
src-676d10cd15f1c21a- Publisher
- Name not classified · datosabiertos.bogota.gov.co
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-11-03
- Dossier created
- 2026-11-04
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Open-data check, fetched 26 July 2026: 34 datasets, licensed CC BY 4.0 (20), CC BY-SA 4.0 (12) and CC BY-NC-SA 4.0 (2) — the first non-commercial licence encountered in this atlas's licence series. The catalogue covers routes, stations, cable pylons and operational zones. A "Validaciones Tarjeta Tullave – SITP" dataset (search index: last modified 2022) returned HTTP 404 at https://datosabiertos.bogota.gov.co/dataset/validaciones-tarjeta-tullave-sitp and is absent from the current listing, so fare-card boarding data is not published today.
- Claims linked
- Background source; no baseline claim points here
Secretaría Distrital de Movilidad — Sistema Interoperable de Recaudo (SIR)
- Stable source ID
src-79b0302077266227- Publisher
- Name not classified · movilidadbogota.gov.co
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-11-03
- Dossier created
- 2026-11-04
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The city's page for the interoperable collection system (SIR): it is to accept open city cards, bank cards, QR codes, phones and wallets and, transitionally, TuLlave; it is not an upgrade of TuLlave, and TuLlave will keep operating during a gradual transition.
- Claims linked
Publimetro — new collection system changes concessionaire, not dependency (16 Aug 2026)
- Stable source ID
src-fb306868f90ad400- Publisher
- Name not classified · publimetro.co
- Type / language
- web-page · language not classified
- Published
- 2026-08-16
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-11-03
- Dossier created
- 2026-11-04
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Opinion column: the city tendered a five-year concession, estimated at COP 260–310bn, to design, build, run and maintain the interoperable system for TransMilenio, SITP, the metro and Regiotram; the author argues the city still lacks the technical information to make TuLlave directly interoperable.
- Claims linked
Known limits of this file
- Publisher names and source languages have not yet been classified; domains are recorded without guessing.
- Existing source notes are descriptive locators, not page- or paragraph-exact citations.
- A missing archive, publication date or content hash is shown as null rather than inferred.
- The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.
Continue exploring
Compare this project
Explore the wider context
📎 Cite this project
1001 Smart Cities (2026). “TuLlave: Bogotá's concession-run fare card & preloaded free trips” — Bogotá, Colombia. The Smart City Atlas. https://1001smartcities.org/projects/bogota-tullave-fare-card/ (last verified 2026-11-03). Data: CC BY 4.0.
The underlying data is free to reuse with attribution — see the open data page.